                                                     Public Safety

                             Goal 2: Mitigate Flood Risks and Protect Stormwater Infrastructure
                                        Objective 1: Plan and Implement Stormwater Projects
                          Project                   Performance Measure(s)                Department(s)
             Core   Stormwater Projects        Implement projects that mitigate   Public Works & Transportation
             PS                                flooding concerns
             2.1.1
             Summary:
                                                                    Stormwater Capital Improvements   Structures
             Stormwater Projects are funded through the Stormwater             Project               Protected
             Utility Fee and are included in the annual capital budget as   California Lane (All Phases)   60
             well as in the Comprehensive Stormwater Master Plan.    Harvest Hills (All Phases)          47
             The projects listed below include projects that began   Kee Branch Trib 4 (All Phases)     N/A
             construction prior to FY 2022 as well as the planned FY   Matthews Court (All Phases)       74
             2022 projects. Project milestones listed in the table will be
             updated as they occur during the year.  These projects
             include larger drainage and erosion projects. Maintenance
             projects and small drainage improvement projects are not
             included in this report because they are typically bid in
             multiple phases.


                     Stormwater Capital Improvement Project      Estimated   Actual Bid   Estimate    Actual
                                                                 Bid Dates    Dates     Completion   Completion
              California Lane Drainage Improvements Phase 1    June 2022
              Harvest Hills Drainage Improvements Phase 1      Aug. 2019
              Indian Trail Erosion                             Mar. 2020    May 2020   Oct. 2021
              Kee Branch Trib 4 Erosion Phase 2 – Bradley to Andalusia    Dec. 2020   Aug. 2021   Jan. 2023
              Matthews Court Drainage Improvements Phase 1 and 2   June 2019   Dec. 2019   Mar. 2021
              Matthews Court Drainage Improvements Phase 3     Dec. 2021
             .