                        GOALS, OBJECTIVES AND PERFORMANCE MEASURES
                                                       2020-2021


            PUBLIC SERVICES

                        ANNUAL OBJECTIVES                                2019-2020 PERFORMANCE
            On call personnel will respond to calls within 30 minutes  Personnel responded to all calls for service.
            after receiving the call 100% of the time.
            Replace stolen or damaged signs within 7 days.   100% of signs were replaced within 7 days.
            Repair 75% of the pot holes within 7 days.       100% of pot holes were repaired within 7 days.
            Replace broken sidewalks as scheduled.           100% of sidewalks on the schedule were replaced.
            Clean debris from all streets twice a year.      Streets were cleaned twice in FY2019-2020.


            Respond to weather emergencies (sand streets, set up Personnel were on call to respond to emergiencies during
            barricades, etc.) in a timely manner.            inclement weather.


            Check storm drains monthly.                      100% of the 32 storm drains were checked monthly.

            Clean the six (6) main drainage channels twice a year.  100% of the main drainage channels were cleaned twice in
                                                             FY2019-2020.
            Reduce workers compensation claims by promoting There was one workers compensation claim.
            safety on the job.





                                                             2016-2017 2017-2018 2018-2019 2019-2020 2020-2021
                        PERFORMANCE MEASURES
                                                              ACTUAL    ACTUAL     ACTUAL    ACTUAL    BUDGET
            STREETS
            Scheduled Sidewalk Repairs Completed               100%       100%      100%       100%      100%
            Linear Feet of Concrete Paving Installed           26,899    31,692     3,057     2,179      5,000
            Pot Holes Repaired                                   33        53        562       783        100
            Crack Seal Streets (Linear Feet)                     0       30,000    30,000       0       30,000
            DRAINAGE
            Culverts Cleaned (Feet)                            1,200      3,280     5,100      2,350     2,000
            Percent of Storm Drains Checked Monthly (32)       100%       100%      100%       100%      100%
            BUILDING MAINTENANCE
            Building Maintenance Jobs Completed                 206        329       543       293        400
            Sprinkler System Maintenance/Repair Jobs             33        40        20         19        30
            OTHER
            Contract Mowing Expenditures                      $147,030  $126,236  $100,476   $114,159  $220,000
            Workers Compensation Claims                          2          1         3         1          0