Page 43 - N. Richland Hills Capital Budget
P. 43

Street & Sidewalk Capital Projects
        Department                                             Project Title                         Project Number
        Public Works                                Davis Blvd/Mid-Cities Blvd Intersection               ST0401
        Project Description
        This project consists of intersection improvements at the Davis Blvd and Mid-Cities Blvd Intersection.  The improvements include
        adding additional right and left turn lanes, signalization improvements, and all necessary water and sewer main adjustments. This
        project is a 2003 Bond Program Project.







        Project Justification
        This intersection is located on a major east/west and north/south thoroughfare that runs through NE Tarrant County. Heavy traffic
        congestion is experienced during peak hours.  As of 2006, more than 53,000 vehicles travel through this intersection per day.  In the
        future, this intersection will experience significant development which will add to the traffic congestion.  Improvements to this
        intersection will reduce the traffic congestion and provide added capacity to handle future traffic volumes.

        Note: The Congestion Mitigation and Air Quality (CMAQ) grant reimburses the City after each invoice is paid. The TXDOT
        reimbursement takes about 90 days. The Engineering/Design schedule shown for this project also includes the necessary time for all
        public meetings as well as the time for the mandatory Environmental Assessment (EA) that typically takes 6 to 10 months.
        Additional TxDot requirements have resulted in a scope and budget change which increased the original funding by an additional
        $1,625,000. The additional funding consists of: $1,150,000 NCTCOG Grant and $475,000 of project savings from recently
        completed projects.

        FY17/18 Adopted funding requests are from: General Obligation Bonds ($550,000), TxDot and Federal Grants ($395,018), and
        Utility Fund Reserves ($557,000).  FY 17/18 Revised funding requests are from: RTC TIP Grant ($525,190), Certificate of Obligation
        Bonds ($131,297)
        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services      10/2003      05/2008   Adopted Budget    2003-04      $2,000,000
        Engineering/Design         07/2008      10/2014   Revision          2010-11      $1,625,000
        Land/ROW Acquisition       08/2014      04/2017   Adopted Budget    2014-15      $1,575,726
        Construction               06/2017      07/2019   Adopted Budget    2016-17      $1,502,018
        Other                                             Revision          2017-18       $656,487
        Total Schedule             10/2003      07/2019   Revision          2018-19       $330,769
        Sources of Funds          To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Funding
        General Obligation Bonds    1,050,000           0             0             0     $1,050,000
        Certificates of Obligation    630,000           0             0             0      $630,000
        Federal/State Grants        4,746,750           0             0             0     $4,746,750
        Reserves                    1,013,250           0             0             0     $1,013,250
        Sales Tax
        Other                         250,000           0             0             0      $250,000
        Total Funding              $7,690,000          $0            $0            $0     $7,690,000
        Project Costs             To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Cost
        Professional Services         107,000           0             0             0      $107,000
        Engineering/Design            672,493           0             0             0      $672,493
        Land/ROW Acquisition          400,000           0             0             0      $400,000
        Construction                5,610,518           0             0             0     $5,610,518
        Other                         899,989           0             0             0      $899,989
        Total Costs                 $7,690,000         $0            $0            $0     $7,690,000
        Operating Impact
        No additional impact is projected with this project.


        Fiscal Year                2020-21       2021-22      2022-23       2023-24       2024-25     Total Impact
        Amount                           $0            $0            $0            $0            $0            $0
        Total Operating Impact           $0            $0            $0            $0            $0            $0




                                                             41