Page 260 - N. Richland Hills Capital Budget
P. 260

Major Capital Equipment Capital Projects
        Department                                             Project Title                         Project Number
        Information Services                      Enterprise Computer System Replacement                  IT1701
        Project Description
        This project is for the purchase and replacement of the current enterprise computer system serving the city of North Richland Hills.










        Project Justification
        The City of North Richland Hills currently has the Superion Public Sector enterprise resource planning system.  Modules currently in
        use are those related to accounting/finance, purchasing, budget, utility billing, building permits, fleet management and licenses.  The
        City has utilized Superion since 1998.  Both business and technology needs have changed dramatically since implementation of
        Superion.  With a new system costs should be reduced, it will improve decision making by providing easier access to information,
        improve customer service both internally and externally, improve efficiency and effectivenes of business operations and improve
        accountability.
        Note : FY 2016-2017 funding from Information Technology Reserves.  2018-2019 funding is Certificates of Obligation. FY 2018-
        2018 Funding from Information Technology Reserves. FY 2019-2020 Funding from General CIP Reserves (305) $204,448, IT
        Capital Project Fund Reserves (386) $221,000, and $75,000 from Information Technology Reserves (520).







        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services      02/2018      09/2018   Adopted Budget    2016-17        $95,000
        Engineering/Design                                Proposed          2018-19      $2,905,000
        Land/ROW Acquisition                              Revision          2018-19       $173,980
        Construction                                      Revision          2019-20       $500,448
        Other                      10/2018      04/2021   Total                          $3,674,428
        Total Schedule             02/2018      04/2021
        Sources of Funds          To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation  2,905,000           0             0             0     $2,905,000
        Federal/State Grants
        Reserves                      769,428           0             0             0      $769,428
        Sales Tax
        Other
        Total Funding              $3,674,428          $0            $0            $0     $3,674,428
        Project Costs             To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Cost
        Professional Services         360,205           0             0             0      $360,205
        Engineering/Design
        Land/ROW Acquisition
        Construction
        Other                       3,314,223           0             0             0     $3,314,223
        Total Costs                 $3,674,428         $0            $0            $0     $3,674,428
        Operating Impact
        Operating impact will be determined at a future date when new system is implemented.


        Fiscal Year                2020-21       2021-22      2022-23       2023-24       2024-25     Total Impact
        Amount                           $0            $0            $0            $0            $0            $0
        Total Operating Impact           $0            $0            $0            $0            $0            $0




                                                             244
   255   256   257   258   259   260   261   262   263   264   265