        Department                                             Project Title                         Project Number
        Parks and Recreation                          Linda Spurlock Park Renovation                      PK1902
        Project Description
        This project involves the redevelopment of the existing neighborhood park through the design and construction of existing and new
        amenities based on stakeholder input meetings. Recommended park elements for the renovation of the park include a new parking
        lot, a new pavilion, upgrade of playground equipment and support facilities.







        Project Justification
        The Linda Spurlock Park Renovation Project was the number 2 priority identified in the 2016 Updated Park System Master Plan
        Priorities. The 10 acre park is 24 years old, and the amenities are aged and in need of renovation. The renovation project will
        provide the opportunity to correct many long term infrastructure maintenance issues while emphasizing positive aspects of the park
        site.

        Note: Funding source for FY2019 & FY 2020 - Sales Tax ($135,000) and Park Impact Fee Reserves ($89,000). Funding source for
        FY2020 - Sales Tax Reserves ($811,000).











        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Adopted Budget    2018-19       $189,000
        Engineering/Design         10/2018      04/2020   Proposed          2019-20       $811,000
        Land/ROW Acquisition                              Revision          2019-20        $35,000
        Construction               05/2020      12/2020   Total                          $1,035,000
        Other
        Total Schedule             10/2018      12/2020
        Sources of Funds          To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves                      900,000           0             0             0      $900,000
        Sales Tax                     135,000           0             0             0      $135,000
        Other
        Total Funding              $1,035,000          $0            $0            $0     $1,035,000
        Project Costs             To Date    2020-21 Budget 2021-22 Estimate  2022-Completion  Total Cost
        Professional Services
        Engineering/Design            148,690           0             0             0      $148,690
        Land/ROW Acquisition
        Construction                  886,310           0             0             0      $886,310
        Other
        Total Costs                 $1,035,000         $0            $0            $0     $1,035,000
        Operating Impact
        None.


        Fiscal Year                2020-21       2021-22      2022-23       2023-24       2024-25     Total Impact
        Amount                           $0            $0            $0            $0            $0            $0
        Total Operating Impact           $0            $0            $0            $0            $0            $0




                                                             185
   190   191   192   193   194   195   196   197   198   199   200