Page 19 - Grapevine Budget FY21
P. 19

Goal:  Address future transportation needs

               •  The FY21 budget provides funding fort the City’s participation in a Local Project Advanced
                   Funding Agreement (LPAFA) with the Texas Department of Transportation (TxDOT) for the
                   widening of Euless Grapevine Road from two lanes to four lanes with a new traffic signal at
                   the intersection of the SH 360 Frontage Road.

               •  The FY21 budget also provides funding fort the City’s participation in a LPAFA with TxDOT
                   for the widening of Fairway Drive from two lanes to three lanes with a new minim ten-foot
                   wide shared use path from SH 26 to Marina Drive.

               •  Continued participation in the partnership between Grapevine and Trinity Metro in support of
                   the  TEXRail commuter rail  program.   The FY21  budget  allocates 3/8-cent of  4B sales tax
                   collections ($8.7 million) in payments to Trinity Metro.


               Goal:  Continue to enhance tourism development

               •  Stand Rock Phase 1: 490 rooms and 100 timeshare units - $160 million project.
               •  Meow Wolf: Major entertainment complex to be located at Simon’s Grapevine Mills Mall -
                   $30 million project.
               •  Southland Holdings: Headquarters relocation - $5 million project.
               •  Grapevine Main – Train station opening: $110 million project.
               •  Payton Wright  redevelopment: Multiple restaurant concepts on old Payton Wright  Ford
                   dealership property.
               •  Hilton Inn – Silver Lake: 152 guest rooms


               Goal:  Invest in “Quality of Life” capital projects

               •  The FY21 budget includes funding for the design, production and installation of a large scale
                   custom 3-piece Christmas Train display to be installed at the Peace Circle plaza outside of the
                   Grapevine Main train station.

               •  FY21 projects includes allocations for Grapevine’s continued participation in TxDOT’s Green
                   Ribbon highway beautification project.






















                                                             11