Page 271 - Colleyville FY21 Budget
P. 271

Exhibit C 5 Year Capital Improvement Plan  Fiscal Year 2021‐2025  *Impact Fees ‐  *Impact Fees ‐  **Water Impact  **Wastewater  Tomorrow  Tomorrow Fund  Voluntary  Parkland   TIF Voluntary Park Area II (West of  Area I (East of  *FHA/TxDOT  Fees Impact Fees Fund ‐ Parks  ‐ City  Library Dedication Fund  26)  26)  $2,709,176 $743,504 $870,000  $112,912 $468,013  $399,567  $54,043  $37,603 $1,345,920 $199,853  $0  $0  $0  $0  $0  $100,000  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $400,000  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $700,000  $0







                   Drainage Fund  ‐$142,051  $0  $0  $0  $0  $0  $300,000  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $300,000  $200,000  $0  ‐$242,051  $0  $0  $0  $300,000  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $300,000  $200,000  $0






                 CEDC (Parks,   Trails &   Libraries)  $995,296  $300,000  $0  $0  $0  $0  $0  $1,000,000  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $1,300,000  $0  $1,568,445  $2,338,901  $465,752  $300,000  $0  $0  $0  $0  $0  $0  $75,000  $0  $0  $0  $0  $0  $0  $375,000  $0  $1,591,974  $2,381,077






                   **Utility Fund  $1,044,686  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $200,000  $0  $1,800,000  $0  $2,000,000  $531,100  $1,038,457  $614,243  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $0  $1,700,000  $200,000  $1,900,000  $531,100  $1,301,597






                  Capital Projects   Fund  ‐$1,348,456  $0  $250,000  $0  $200,000  $0  $50,000  $0  $400,000  $0  $50,000  $75,000  $0  $0  $400,000  $500,000  $100,000  $0  $650,000  $700,000  $1,200,000  $4,575,000  $500,000  $1,259,827  $2,202,895  ‐$1,960,734  $0  $250,000  $0  $1,500,000  $50,000  $400,000  $50,000  $75,000  $0  $750,000  $400,000  $500,000  $100,000  $0  $0  $4,075,000  $500,000  $4,800,000  $1,702,598






                   Total Project Cost  $400,000  $250,000  $400,000  $200,000  $700,000  $500,000  $1,000,000  $400,000  $2,500,000  $50,000  $75,000  $234,000  $1,000,000  $400,000  $500,000  $100,000  $200,000  $2,550,000  $2,500,000  $1,200,000  $15,159,000  $400,000  $250,000  $350,000  $1,500,000  $500,000  $400,000  $50,000  $75,000  $75,000  $750,000  $400,000  $500,000  $100,000  $1,700,000  $200,000  $7,250,000











                        Estimated 10/1/2022 Available Balance  Cheek‐Sparger Trail  City Hall ‐ Boiler Replacement  Dog Park/Splash Pad Drainage Improvements FY2023 Kimzey Park Playground Improvements Misc Concrete Rehabilitation‐2023 Nature Center Trail PH2‐Construction Parking Facility Pavement Marking‐2023  Rehabilitate the Historic Fire Station Senior Center Renovations‐2023 Street Maintenance County‐2023 Street Maintenance Program‐2023 Street Pavement Marking‐2023  (+) Year‐end surplus contributions  (‐/+) Transfers in/out (+) FY24 Budgeted Contribution Estimated 10/1/2023 Available Balance  Bedford Road Trail ‐ Constru



                   Title   Annual Sidewalk/Trail Construction/Grant Match FY2 Annual Small Segment Sidewalk/Trail Construction   Parkway Tree Removal and Replacement‐2023  Water Project 14: Mixed Use Connections‐Design Water Project 5: Brighton Oaks Water/Street Rehabil Water Project 16: Timberline Drive ‐ Construction Woodbriar/Quail Crest Street Rehabilitation (Compan  Sum Of Total Project Cost:  (‐) Operational Costs not included in project list  Annual Sidewalk/Trail Construction/Grant Match FY2 Annual Small Segment Sidewalk/Trail Construction  City Hall and Library Exterior Cleaning and Sealing  Parkway Tree Removal and










                   Year  2023  FY2023                                                       2024  FY2024                                                      9/8/2020  1:48 PM
   266   267   268   269   270   271   272   273   274   275   276