park Row Project Fund This fund was created by advice from the Town's auditors to help centralize
revenues, transfers and expenditures related to the Park Row Project for the duration of the project. The
project consists of the rehabilitation of the Park Row corridor which is to include: new streets, sidewalks,
waterline upgrades, lighting and crosswalks. This project has begun and budgeted expenditures for FY
2019-2020 are $738,875.
WATER AND SEWER FUND
The Water and Sewer enterprise fund receives all revenue through monthly utility customer billings.
Expenses of the Water and Sewer fund include all activities necessary to provide water and wastewater
services to the citizens of Pantego. The Water and Sewer Fund is divided into four (4) separate
funds: (1) Water and Sewer Operations Fund, (2) Sewer Construction Fund, (3) Water
Infrastructure Fund, and (4) a newly created fund to track the Enterprise Fund's portion of projects
funded by the 2019 issuance of Certificates of Obligation. The fund is designed to make a profit, any
excess revenue after the general expenses are paid, are accumulated as reserves or transferred to
the Water and Sewer Construction Fund for future use.
Water and Sewer Operatjnq fund The Water and Sewer Fund has a separate Budget for the
operation of water and sewer services. Revenue resources include water sales, sewer service charge
fees, groundwater conservation fees, collection of garbage and recycling fees, tap fees, water and
sewer access fees, late fees and investment income. The Town currently outsources services for
garbage and recycling; therefore, and per contract, the Town charges and collects the fees and remits
the amount collected to the contractor. Payments are made from this fund for the general operation
and maintenance of the water and sewer system. The fund is designed to make a profit, any excess
revenue after the general operating expenses are paid, are accumulated as reserves/unrestricted net
position.
Overall, water and sewer revenues for Fiscal Year 2019-2020 are projected to increase because of a
recommended rate increase in accordance with the most recent rate study conducted in 2016. Water
sales are projected at $569,605, a slight decrease of $6,292 under the current year's adopted
Budget. Sewer service charge fees are projected at $561,679 $81,122 more than the current year
adopted Budget. These projections are based on historical data and trends included in the rate study.
Sewer Construction Fund The purpose of this fund is to account for transfers from the Water and
Sewer Operating Fund to be used for improvements and repairs to the sewer system. The Fiscal Year
2019-2020 does not include any budgeted items.
Water Infrastructure Fund - This fund was created in Fiscal Year 2011-12 (Ordinance 12-687) by the
Town Council under the advice of the Town's Ad-hoc Water Committee. The objective of the fund is to
generate revenue from the water sales by applying a specific charge that is based on the amount of
water each customer consumes and use it to pay for the water and sewer infrastructure projects
identified by the water study commissioned by the Town Council. Revenue from Infrastructure fees are
projected at $315,000. The Fiscal Year 2019-2020 projects are budgeted at $50,000.
2019 CO Water and Sewer Capital Projects Fund This fund was created to keep track of the
funds received from the 2019 issuance of Certificates of Obligation due to the fact those Obligations
were issued for a specific purpose. The improvements planned to be funded by those funds are: