Page 95 - NRH FY20 Approved Capital Budget
P. 95

Drainage Capital Projects
        Department                                             Project Title                         Project Number
        Public Works                                  Emerald Circle Drainage Project                    DR1901
        Project Description
        This project consists of extending an underground storm drain system in the Emerald Lakes subdivision.










        Project Justification
        The Emerald Lakes subdivision was constructed south of Emerald Hills way, across the street from Carrie Frances Thomas
        Elementary School back in the 1990s.  Since construction, the northeast quadrant of the subdivision has experienced settling under
        the roadway, creating significant ponding issues after moderate rain events.  A detailed topographic survey revealed that the extent
        of pavement reconstruction necessary to address the ponding would be significant, and would result in excessively flat gutter
        grades.  Extending a storm drain system to this area will provide a more reliable long-term solution.

        Note: FY 18-19 Funding comes from Drainage Utility Fund Reserves (120).











        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Adopted Budget    2018-19       $130,000
        Engineering/Design         12/2018      04/2019   Total                           $130,000
        Land/ROW Acquisition
        Construction               06/2019      11/2019
        Other
        Total Schedule             12/2018      11/2019
        Sources of Funds          To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves                      130,000           0             0             0      $130,000
        Sales Tax
        Other
        Total Funding                $130,000          $0            $0            $0      $130,000
        Project Costs             To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Cost
        Professional Services
        Engineering/Design            30,000            0             0             0       $30,000
        Land/ROW Acquisition
        Construction                  100,000           0             0             0      $100,000
        Other
        Total Costs                  $130,000          $0            $0            $0      $130,000
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2019-20       2020-21      2021-22       2022-23       2023-24     Total Impact
        Amount                            $0           $0            $0            $0            $0            $0
        Total Operating Impact            $0           $0            $0            $0            $0            $0