Page 79 - NRH FY20 Approved Capital Budget
P. 79

Street & Sidewalk Capital Projects
        Department                                             Project Title                         Project Number
        Public Works                             Northeast Parkway / Davis Blvd. Traffic Signal           ST2003
        Project Description
        This project consists of engineering and construction of a new traffic signal at the intersection of Davis Boulevard and Northeast
        Parkway.  The scope includes paving and signal improvements.









        Project Justification
        The Northeast Parkway / Davis intersection lies within the Smithfield Transit Oriented Development and serves a large residential
        area east of Davis.  The addition of a signal would provide for safe access during peak times from Northeast Parkway to Davis
        Boulevard for the Stonybrooke neighborhoods, the new Smithfield Villas TOD residential neighborhood, and the existing industrial
        users on Northeast Parkway.  Based on the future extension of Northeast Parkway to the west, it is expected that even more
        motorists will use this intersection in the future.

        Funding Source: Certificates of Obligation.











        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Proposed          2019-20       $380,000
        Engineering/Design         10/2019      03/2020   Total                           $380,000
        Land/ROW Acquisition
        Construction               04/2020      01/2021
        Other
        Total Schedule             10/2019      01/2021
        Sources of Funds          To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation        0        380,000            0             0      $380,000
        Federal/State Grants
        Reserves
        Sales Tax
        Other
        Total Funding                     $0       $380,000          $0            $0      $380,000
        Project Costs             To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Cost
        Professional Services
        Engineering/Design                0         80,000            0             0       $80,000
        Land/ROW Acquisition
        Construction                      0        300,000            0             0      $300,000
        Other
        Total Costs                       $0       $380,000          $0            $0      $380,000
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2019-20       2020-21      2021-22       2022-23       2023-24     Total Impact
        Amount                            $0           $0            $0            $0            $0            $0
        Total Operating Impact            $0           $0            $0            $0            $0            $0




                                                             75