Page 178 - NRH FY20 Approved Capital Budget
P. 178

Parks & Recreation Capital Projects
        Department                                             Project Title                         Project Number
        Parks and Recreation                             Annual Tree Planting 2019                        PK1901
        Project Description
        This project provides for the introduction of trees into the urban forest and replacement of trees that have died at various locations
        throughout the City. The project involves the installation of 3" caliper, drought tolerant, native or adapted trees. Park facilities to
        receive trees includes Northfield Park and various other locations.







        Project Justification
        The urban forest is an important part of the City's landscape. It's made up of all the public trees in North Richland Hills. Trees add to
        the wellbeing of our community by moderating our local climate, filtering air pollutants, storing storm water and reducing run-off,
        raising  property values, and provides years of beauty and stress relief.
        This project allows for the continued maintenance and growth of our urban forest through the introduction of approximately 45 native
        or adapted trees focusing on restoration of areas having undergone recent construction activities, such as Northfield Park.
        Project funding is from Park Sales Tax.










        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Adopted Budget    2018-19        $45,000
        Engineering/Design                                Total                            $45,000
        Land/ROW Acquisition
        Construction               10/2018      05/2019
        Other
        Total Schedule             10/2018      05/2019
        Sources of Funds          To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves
        S  a  l  e  s     T  a  x     4  5  ,  0  0  0  0             0             0       $45,000
        Other
        Total Funding                 $45,000          $0            $0            $0       $45,000
        Project Costs             To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                  45,000            0             0             0       $45,000
        Other
        Total Costs                   $45,000          $0            $0            $0       $45,000
        Operating Impact
        None.


        Fiscal Year                2019-20       2020-21      2021-22       2022-23       2023-24     Total Impact
        Amount                            $0           $0            $0            $0            $0            $0
        Total Operating Impact            $0           $0            $0            $0            $0            $0




                                                             164