Page 157 - NRH FY20 Approved Capital Budget
P. 157

Utility Capital Projects
        Department                                             Project Title                         Project Number
        Public Works                         Conn Pump Station Pump and Electrical Rehabilitation         UT2008
        Project Description
        This project is to reconfigure existing suction header piping and pumps to meet the Hydraulic Institute standard for pipe pumping
        and to upgrade and reconfigure electrical components to meet the National Electric Code.









        Project Justification
        Conn Pump Station provides potable water from the south of the city to just south of Mid-Cities Blvd. The pump station provides
        potable water and pressure to the distribution system through four pumps located on the site. Three of these pumps were replaced 6
        years ago. Staff became aware of noticeable wear and tear on the pumps through inspections and failures. Freese and Nichols
        Engineering group was hired to conduct a piping analysis to determine the cause for the premature pump issues. Through this
        analysis, Freese and Nichols was able to determine that the pump issues were caused by the net positive suction head created by
        the piping alignment on the suction side of the pumps. The suction piping has a 90 degree bend located too close to the pump on
        three of the four pumps. The analysis also shows that the electrical panels will have to be moved to correct the alignment of the
        piping and to meet clearance requirements from the National Electric Code.

        Funding Source: Certificates of Obligation.







        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Proposed          2019-20      $1,500,000
        Engineering/Design         10/2019      09/2020   Total                          $1,500,000
        Land/ROW Acquisition
        Construction               02/2020      09/2020
        Other
        Total Schedule             10/2019      09/2020
        Sources of Funds          To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation        0       1,500,000           0             0     $1,500,000
        Federal/State Grants
        Reserves
        Sales Tax
        Other
        Total Funding                     $0     $1,500,000          $0            $0     $1,500,000
        Project Costs             To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Cost
        Professional Services
        Engineering/Design                0        328,975            0             0      $328,975
        Land/ROW Acquisition
        Construction                      0       1,171,025           0             0     $1,171,025
        Other
        Total Costs                       $0     $1,500,000          $0            $0     $1,500,000
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2019-20       2020-21      2021-22       2022-23       2023-24     Total Impact
        Amount                            $0           $0            $0            $0            $0            $0
        Total Operating Impact            $0           $0            $0            $0            $0            $0




                                                             147
   152   153   154   155   156   157   158   159   160   161   162