Page 145 - NRH FY20 Approved Capital Budget
P. 145

Utility Capital Projects
        Department                                             Project Title                         Project Number
        Public Works                               Small Water Main Replacements (2017)                   UT1705
        Project Description
        This is an annual program that is completed by the Public Works Construction Division.  The project replaces old 2" and 4" water
        mains with 6" or larger water pipes and provides adequate fire hydrant coverage to areas currently without proper coverage.  This
        project will provide for small water main replacement on the following streets:  Circleview Dr. (Lariat to Shady Lake), Meadow Ct.
        (Lola to cul-e-sac), Meadowbrook Dr. (Royal Ridge to Brookridge), Woodcreek Ln. (Lariat to Riviera), and Spring Lea Way (Starnes
        to Lincoln).





        Project Justification
        This is an annual program that is completed by the Public Works Construction Division.  The project replaces old 2" and 4" water
        mains with new 6" or larger water pipes and provides adequate fire hydrant coverage to areas currently without proper coverage. In
        addition, this project helps to replace water lines that have deteriorated to a point where numerous water line breaks occur.
        .
        Funding source: Utility Operations for Capital Projects














        Project Schedule        Beginning Date  Ending Date  History       Fiscal Year   Amount
        Professional Services                             Adopted Budget    2016-17       $420,000
        Engineering/Design                                Total                           $420,000
        Land/ROW Acquisition
        Construction               10/2016      08/2019
        Other
        Total Schedule             10/2016      08/2019
        Sources of Funds          To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Funding
        General Obligation Bonds
        Certificates of Obligation
        Federal/State Grants
        Reserves                      420,000           0             0             0      $420,000
        Sales Tax
        Other
        Total Funding                $420,000          $0            $0            $0      $420,000
        Project Costs             To Date    2019-20 Budget 2020-21 Estimate  2021-Completion  Total Cost
        Professional Services
        Engineering/Design
        Land/ROW Acquisition
        Construction                  420,000           0             0             0      $420,000
        Other
        Total Costs                  $420,000          $0            $0            $0      $420,000
        Operating Impact
        No operating impact is anticipated.


        Fiscal Year                2019-20       2020-21      2021-22       2022-23       2023-24     Total Impact
        Amount                            $0           $0            $0            $0            $0            $0
        Total Operating Impact            $0           $0            $0            $0            $0            $0




                                                             135
   140   141   142   143   144   145   146   147   148   149   150