FY 2024 - $26,613,600
• Final Expansion-Bud Ervin Water Treatment Plant
• WTP High Service Pump Station Expansion
• Misc. Utilities for Roadway Bond Projects
FY 2025 - $12,814,200
• 42” Sewer Main in Walnut Creek Lower Basin
• 12” Water Line near Northern City Limits
FY 2026 - $4,224,400
• 16” Water Line along Britton Road
• 12” Water Line along Turner Warnell Road
FY 2027 - $5,971,600
• 20” Water Line along US Highway 287
• 36” Sewer Main along Walnut Creek
• 12” Sewer Main near Magnolia Street
FY 2028 - $3,430,500
• 30” Water Line along Lone Star Road
• 10” Sewer Main along US 287
FY 2029 - $8,306,100
• 12/16” Water Line along FM 157 and Chambers Street
• 24/27” Sewer Main along Low Branch Creek