Page 202 - Hurst FY20 Approved Budget
P. 202
CITY OF HURST
GENERAL FUND PUBLIC WORKS 0663 ENGINEERING
MISSION STATEMENT
To provide for effective administration of Public Works activities that ensures safe and efficient
roadway systems and to ensure that all City public paving improvements are designed and
constructed in accordance with City regulations and accepted engineering and construction
principles and practices.
DIVISION DESCRIPTION
The Engineering Division of the Public Works Department is responsible for the overall
supervision and administration of streets, drainage, engineering, and construction activities. The
Engineering Division is responsible for reviewing and/or preparing construction plans, issuing
permits, and inspecting new construction of all sidewalks and street systems. The GIS staff within
the Engineering Division prepares and maintains a street inventory classification system,
prepares long-range planning for street improvements, and maintains and updates all street
maps.
PRIOR YEAR RESULTS & ACCOMPLISHMENTS
Completed design and began construction of the 44 Year CDBG Grant Project / Sheri
th
Lane from Reed to Cavender.
Completed construction of Pipeline Road Phase 2
Continued with ROW acquisition for Pipeline Road Phase 3.
Applied for Safe Routes to School grant funding through the Texas Department of
Transportation for sidewalk construction near three elementary schools in Hurst
Review of numerous private development projects.
FUTURE INITIATIVES
Complete construction of the 44 Year CDBG Grant Project / Sheri Lane from Reed to
th
Cavender.
Complete ROW acquisition for Pipeline Road Phase 3.
Notify franchised utility companies of conflict/adjustments for Pipeline Road Phase 3.
Begin design of Pipeline Road Phase 4.
186
119