Page 233 - FY2020Colleyville
P. 233

Exhibit A
                                                    City of Colleyville
                                                Capital Improvement Plan
                                                     Fiscal Year 2020
                                                   Project Descriptions


    Master Plans/Studies

    Drainage Fee Assessment Study

    Program Description                                            Strategic Plan Connection
    The purpose of the drainage fee assessment study is to         3.3 Mitigate stormwater runoff and flooding risks
    determine if the rates charged are appropriate.


    Total Project Cost  $50,000
            Category                    Type                       Funding Source                   2020
    Master Plans/Studies    Master Plans/Studies        TIF                                           $50,000.00







    Water Risk and Resilience Assessment
    Program Description                                            Strategic Plan Connection
    This project is for a Water Risk and Resilience Assessment as   3.2 Ensure regular replacement of water and
    per the October 23, 2018 law, America's Water Infrastructure   wastewater facilities
    Act (AWIA). The law requires community (drinking) water
    systems serving more than 3,300 people to develop or
    update risk assessments and emergency response plans
    (ERPs).

    Total Project Cost  $100,000

            Category                    Type                       Funding Source                   2020
    Master Plans/Studies    Master Plans/Studies        Capital Utility Fund                         $100,000.00






    Water, Wastewater, and Roadway Impact Fee Update

    Program Description                                            Strategic Plan Connection
    This project will issue a contract for the technical analysis   3.4 Thoroughly plan for future capital investments and
    required by Chapter 395 of the Texas Local Government code     associated costs
    to determine the maximum water, wastewater, and roadway
    impact fees that may be assessed.

    Total Project Cost  $128,000
            Category                    Type                       Funding Source                   2020
    Master Plans/Studies    Master Plans/Studies        Impact Fees‐Area I (E of SH26)                $32,000.00
    Master Plans/Studies    Master Plans/Studies        Impact Fees‐Area II (W of SH26)               $32,000.00
    Master Plans/Studies    Master Plans/Studies        Wastewater Impact Fees                        $32,000.00
    Master Plans/Studies    Master Plans/Studies        Water Impact Fees                              $32,000.00


                                                                                                          231