CAPITAL PROJECT FUNDS

               Historically, the Capital Improvement Program has preceded development in all areas of the City. The
               Capital Improvement Program is developed with the following guidelines whenever possible:

               The Capital Improvement Program is developed to match costs against expenses occurring in
               corresponding periods of time.  In other words, the development and timing of infrastructure
               improvements is crucial to maintaining current and future developments while maintaining or lowering
               debt ratios. Since 1995, development fees have funded approximately $117,833,688 in improvements.
               Development fees offset the amount of borrowings in the Street and Utility Construction funds.

               The impact of infrastructure improvements on operating and maintenance costs is evaluated and measured
               annually during the budget development process and during revisions to the Long Term Financial Plan.
               Operating and Maintenance cost impacts  in FY 2018-2019  are reflected in  increases in  supply costs,
               staffing increases and in additional service requirements related to expansion of existing facilities, new
               facilities and transmission lines.

               Street Construction Fund

               Street and roadway improvements in FY 2018-2019 are budgeted at $12,621,299. Street impact fees will
               be utilized wherever possible to supplement funding for these projects. In FY 2018-2019, the City
               anticipates issuing $10,000,000 in bonds for street improvements as identified by Staff and approved by
               City Council.

               Utility Construction Fund

               Utility improvements in FY 2018-2019 are budgeted at $13,787,112. Revenue bonds, impact fees, and
               operating  cash from  prior  years will  fund these projects.  Water  & Sewer  impact fees will be  utilized
               wherever possible to supplement funding for these projects.

               Building Construction Fund

               Facility improvements in FY 2018-2019  include  $2,662,000  for  design and land acquisition of Fire
               Station #5, Wayfinding Signage, Downtown Master Plan and Man House renovations.

               MPFDC Construction Fund

               Park improvements in FY 2018-2019 are budgeted at $5,090,000 of which $2,775,000 is for the design
               and construction of the Walnut Creek Linear Park. Other projects include a Dog Park and Pond Branch
               Linear Park Phase II.

               MEDC Construction Fund

               Economic Development projects in the amount of $3,000,000 are budgeted for FY 2018-2019 for
               development of the Mansfield International Business Park.

               Equipment Replacement Fund

               Vehicles, equipment and  technology improvements in FY 2018-2019  are estimated to be  between
               $800,000 and $1,000,000 based on historical averages.