Actual     Adopted     Projected    Adopted
             STAFFING                                 Class Range    FY2017      FY2018      FY 2018     FY 2019
             Director of Public Works                 2601    86       1           1           1            1
             Assistant Public Works Director /Operations  2602  77     1           1           1            1
             Assistant Public Works Director /City Engineer  2602  77  1           0           0            0
             Director of Customer Service*            2602    77       1           1           1            0
             City Engineer                            2804    73       0           1           1            1
             Assistant Director of Finance/Customer Service* 2103  70  0           0           0            1
             Environmental Specialist                 2701    67       1           1           1            1
             Engineer                                 2802    67       1           1           1            1
             Utilities Construction Supervisor        2903    62      0.5         0.5          0.5         0.5
             Water/Sewer Maintenance Supervisor       2904    62       1           1           1            1
             Water Production and Facilities Supervisor  2902  62      1           1           1            1
             Database Administrator                   2801    53       1           1           1            1
             Supervisor of Water Department           2302    51       1           1           1            1
             Construction Inspector                   2803    50       2           2           2            2
             Public Works Crewleader                  2905    48       4           4           4            4
             Senior Equipment Operator*               2906    43       1           1           1            1
             Administrative Secretary                 2003    41       1           1           1            1
             Water Production Operator                2907    41       4           4           4            4
             Water Service Representative**           2912    40       0           1           1            2
             Equipment Operator                       2910    40       1           1           1            2
             Customer Service Representative***       2304    37       4           4           1            1
             Public Works Dispatch Clerk              2702    36       1           1           1            1
             Public Works Maintenance Worker          2911    36       10          11          11          11
             Water Meter Reader**                     2305    35       3           3           2            0
             Total                                                    41.5        43.5        39.5        39.5
             *Replaced Director of Customer Service by Assistant Director of Finance/Customer Service in FY2019
             **Moved 1 Water Meter Readers to Water Service Representatives and closed all Meter Reader positions.
             ***Closed 3 Customer Service Representative positions.

                                                              Actual        Actual       Estimate       Target
             PERFORMANCE MEASURES                             FY2016        FY2017        FY2018        FY2019
             Percent of permitted industries with no wastewater   90%        100%          94%           100%
             discharge violations
             New water mains and services installed (feet)     1,000         1,000          990          2,000
             New sewer mains and services installed (feet)     1,000           0            70           1,000
             Feet of sewer lines cleaned                      250,000       260,000       150,000       200,000
             Feet of sewer mains televised                    100,000       150,000       100,000       175,000
             Number of water main break repairs performed       84            85            50            45
             Number of sewer main break repairs performed       12            15            15            15
             Number of water meters replaced                   893           764          12,830         125
             Billions of gallons of water purchased            1.57          1.58          1.67          1.70
             Billions of gallons of sewage collected           1.86          1.42          1.36          1.40


                        New Water and Sewer Mains                        Water Purchased and Sewer Collected
              2,500
                                                                  2.00
              2,000                                               1.80
                                                   2,000                     1.86
              1,500                                               1.60                      1.67       1.70
                                                                        1.57      1.58
              1,000                                               1.40
                     1,000 1,000   1,000   990          1,000                          1.42                1.40
               500                                                1.20                           1.36
                                     0         70
                 0                                                1.00
                       2016      2017      2018       2019                2016      2017       2018      2019
                         New Water Mains and Services Installed              Billions of Gallons of Water Purchased
                         New Sewer Mains and Services Installed              Billions of Gallons of Sewage Collected
                                                          Page 124