               1.   FM 730 South Water Line Extension

                    This project consists of the construction of an 8-inch water line to be installed along FM 730 South
                    from Main Street to the Cottonwood Creek housing  development.  Currently,  water service is not
                    available in this area and is an obstacle to both residential and commercial development.
                    Additionally, the installation of this line will allow for the water system to be properly looped which
                    improves water quality and will reduce the need for additional water line flushing in the area.  The
                    layout and design will include all valves, fire hydrants, and casing for necessary boring to install a
                    section of the line beneath Ash Creek.

                    Cost:                     $550,000

                    Funding Source:           Water Impact Fees
                                              Prior Year Bond and C.O. Funds

                    Operating Budget Impact:   No  direct financial impact on the operating budget  is expected as a
                                              result of this project.  No additional staff will be required as a third-party
                                              contractor  will  be  hired  to  perform  the  construction.    Current  staff
                                              members will be involved with the project and they must dedicate time
                                              to oversee the project  which does take staff time away from routine
                                              duties creating an indirect impact on the operating budget.

                    Department:               Administration
                                              Utility Maintenance


               2.   Main Street Water Line Improvements

                    This project consists of the upgrade of the existing water line on Main Street.  The existing 10,500
                    linear foot  water  line  is made  up  of various sizes of pipe ranging from  2-inches to 8-inches in
                    diameter and is mainly constructed of cast iron.  The line will be upgraded to a 10-inch PVC line
                    throughout which will greatly enhance water pressure and water quality in the Main Street area.

                    Cost:                     $1,230,000

                    Funding Source:           2017 SWIFT Fund Bond Issuance Proceeds

                    Operating Budget Impact:   No direct financial impact on the operating budget is expected as a
                                              result of this project.  No additional staff will be required as a third-party
                                              contractor  will  be  hired  to  perform  the  construction.    Current  staff
                                              members will be involved with the project and they must dedicate time
                                              to oversee the project  which does take staff time away from routine
                                              duties creating an indirect impact on the operating budget.

                    Department:               Utility Maintenance
                                              Administration